手动计划的任务会及时移动,但事实并非如此。这是为什么?

发布于 2024-10-31 13:24:55 字数 265 浏览 3 评论 0原文

我预计手动计划的任务不会自动更改其日期,尽管项目中发生了所有其他事情。我的老板说会议将在某个固定日期举行。所有之前和之后的任务都必须调整到该日期。

在会议日期之前操纵任务日期会不断地“一遍又一遍”地更改会议的固定日期。我还必须记住,会议日期可能会更改,恕不另行通知。如果我的项目中有 5 个会议怎么办?

这种行为给我的项目工作带来了很多麻烦。我花了1个工作日的时间来准备40个任务的项目。

请帮我解决这个问题。看来我的工作没有成效。这是为什么?

克里斯

I expected that manualy scheduled tasks will not change their dates automatically despite of all other things happened in the project. My Boss says that meeting will be at some fixed date. All previous and later tasks must adjust to that date.

Manipulating the task dates prior to the meeting dates constantly change the fixed dates of the meetings "over and over". I must still remember that the meeting dates might be changed without notice. And what if I have 5 meetings in my project?

That behaviour makes lots of dalay in my work on my project. It takes me as lot as 1 working day of work to prepare 40 task's project.

Help me with this, please. It seems my work is not effective. Why is that?

Chris

如果你对这篇内容有疑问,欢迎到本站社区发帖提问 参与讨论,获取更多帮助,或者扫码二维码加入 Web 技术交流群。

扫码二维码加入Web技术交流群

发布评论

需要 登录 才能够评论, 你可以免费 注册 一个本站的账号。

评论(2

海风掠过北极光 2024-11-07 13:24:55

我猜测您正在使用 MS Project 2010,它引入了“手动计划任务”作为“具有不灵活约束的自动计划任务”的独立概念。

在“选项”对话框下 ->计划选项卡 ->标记为“此项目的计划选项”的部分,查找标记为“编辑链接时更新手动计划任务”的复选框。如果选中此框,可能会导致手动计划的任务按照您的描述移动,因此请确保未选中它。

希望有帮助。

I am guessing that you are using MS Project 2010, which introduces "Manually scheduled tasks" as a separate concept to "Auto-scheduled tasks with inflexible constraints".

Under the Options dialog -> Schedule tab -> Section labelled "Scheduling options for this project", look for a check box that is labelled "Update Manually Scheduled tasks when editing links". If this box is checked, that may result in manually scheduled tasks being moved around as you described, so make sure that it is unchecked.

Hope that helps.

呢古 2024-11-07 13:24:55

这取决于约束的类型。有

  • 灵活、
  • 半灵活、
  • 不灵活

我假设您正在使用半灵活约束,而您确实想使用不灵活约束。 Microsoft 的在线帮助描述了 约束 详细信息 - 这应该可以解决您的问题。

This depends on the kind of constraint. There are

  • Flexible
  • Semi-Flexible
  • Inflexible

I'd assume you're using a semi-flexible constraint while you really want to use an inflexible one. Microsoft's online help describes constraints in detail - this should solve your problem.