which values do we need and which calculation creates the chart?
I guess crauscher already answered this question but I just wanted to say that there are tons of tools out there which can create the burndown for you automatically. All your Team has to do is enter and burn down hours during the Sprint. Although Agile suggests to prefer interactions and use less tools, if you really want to scale as a project/company you would need some sort of Agile project management software. A few I can recommend are : Scrumworks, Piviotal Tracker, Agilex.
发布评论
评论(3)
您需要
现在您可以计算理想线。第一天没有完成任何任务。最后一天所有任务都应该完成。
该图表绘制了每天未完成的任务时间。
就是这样。
You need
Now you can calculate the ideal-line. On the first day no task is accomplished. On the last day all tasks should be accomplished.
The chart draws the task-hours that are not accomplished for each day.
That's it.
这是我写的关于管理燃尽图的完整教程,包括谷歌文档模板和微软 Excel 模板
http://joel.inpointform.net/software-development/burn-down-charts-tutorial-simple-agile-project-tracking/
Here is a whole tutorial I wrote up on managing burn down charts including a google docs template and a microsoft excel template
http://joel.inpointform.net/software-development/burn-down-charts-tutorial-simple-agile-project-tracking/
我想克劳舍已经回答了这个问题,但我只是想说,有大量的工具可以自动为你创建燃尽图。您的团队所要做的就是在 Sprint 期间输入并消耗时间。尽管敏捷建议更喜欢交互并使用更少的工具,但如果您确实想扩展为项目/公司,您将需要某种敏捷项目管理软件。我可以推荐的一些是:Scrumworks、Piviotal Tracker、Agilex。
I guess crauscher already answered this question but I just wanted to say that there are tons of tools out there which can create the burndown for you automatically. All your Team has to do is enter and burn down hours during the Sprint. Although Agile suggests to prefer interactions and use less tools, if you really want to scale as a project/company you would need some sort of Agile project management software. A few I can recommend are : Scrumworks, Piviotal Tracker, Agilex.